Problemática durante la ejecución de una obra bajo la modalidad de administración indirecta en la Universidad Nacional Agraria La Molina

dc.contributor.advisorRodriguez Silva, Gustavo Eduardo Andrés
dc.contributor.authorVigo Gonzales, Nátali Flor
dc.date.accessioned2025-12-10T16:13:41Z
dc.date.available2025-12-10T16:13:41Z
dc.date.issued2025
dc.descriptionUniversidad Nacional Agraria La Molina. Facultad de Ingeniería Agrícola. Departamento Académico de Ordenamiento Territorial y Construcción
dc.description.abstractEl presente Trabajo de Suficiencia Profesional analiza la ejecución de un proyecto de inversión pública realizado bajo la modalidad de administración indirecta, en la Universidad Nacional Agraria La Molina. Durante el desarrollo de la obra, se identificaron deficiencias técnicas y de gestión, principalmente relacionadas con la falta de revisión del expediente técnico antes de la convocatoria, la limitada inversión por parte del contratista, y una deficiente planificación en campo. Estas condiciones generaron incompatibilidades al momento de ejecutar algunas partidas, lo que llevó a la solicitud de adicionales de obra y, como consecuencia, a ampliaciones de plazo. El avance físico alcanzado fue de apenas 67.52 %, y se aprobaron seis ampliaciones de plazo por un total de 225 días, ampliando el plazo contractual a 405 días calendario. El contratista, además, acumuló 62 días de mora luego del vencimiento del plazo contractual, alcanzando la penalidad máxima por mora establecida en la Ley de Contrataciones del Estado. Esto motivó la resolución del contrato por parte de la entidad. Posteriormente, el proyecto fue reactivado bajo el marco de la Ley N.º 31589, permitiendo ejecutar el saldo de obra con un nuevo contratista. A partir del análisis realizado, se concluye que el mayor impacto negativo fue el tiempo, agravado por decisiones internas del contratista y la falta de soluciones rápidas durante la ejecución. Finalmente, se proponen recomendaciones orientadas a mejorar la revisión de expedientes técnicos, fortalecer el control sobre los contratistas, aplicar soluciones a tiempo y asegurar que los saldos de obra reactivados estén bien planificados para garantizar su continuidad.
dc.description.abstractThis Professional Proficiency Report analyzes the execution of a public investment project carried out under the indirect administration modality.in the Universidad Nacional Agraria La Molina. During the development of the project, several technical and management deficiencies were identified, mainly related to the lack of a thorough review of the technical file prior to the bidding process, limited investment by the contractor, and poor on-site planning. These issues led to incompatibilities during the execution of certain project items, resulting in the need for additional works and, consequently, extensions of the contractual deadline. The physical progress reached was only 67.52%, and six time extensions were approved, totaling 225 calendar days and increasing the overall contractual term to 405 days. Furthermore, the contractor incurred 62 days of delay after the deadline, reaching the maximum penalty for delay as established by the Peruvian Public Procurement Law. This situation led the entity to terminate the contract. Subsequently, the project was reactivated under the framework of Law No. 31589, allowing the remaining works to be executed by a new contractor. Based on the analysis, it is concluded that time was the most significant negative factor, worsened by internal decisions made by the contractor and the lack of timely corrective actions during execution. Finally, recommendations are provided to improve the review of technical documents prior to bidding, strengthen contractor oversight, apply timely solutions during execution, and ensure that reactivated project balances are well-planned to guarantee continuity and proper closure.
dc.formatapplication/pdf
dc.identifier.urihttps://hdl.handle.net/20.500.12996/7451
dc.language.isospa
dc.publisherUniversidad Nacional Agraria La Molina
dc.publisher.countryPE
dc.rightsinfo:eu-repo/semantics/openAccess
dc.rights.urihttps://creativecommons.org/licenses/by-nc/4.0/
dc.subjectProyecto de inversión pública
dc.subject.ocdePendiente
dc.titleProblemática durante la ejecución de una obra bajo la modalidad de administración indirecta en la Universidad Nacional Agraria La Molina
dc.typeinfo:eu-repo/semantics/bachelorThesis
dc.type.versioninfo:eu-repo/semantics/publishedVersion
renati.advisor.dni41527785
renati.advisor.orcidhttps://orcid.org/0000-0002-0404-687X
renati.author.dni46129792
renati.discipline811096
renati.jurorAguilar Vidangos, Víctor Filiberto
renati.jurorCuellar Cajahuaringa, Johana Nayeli
renati.jurorBravo Aguilar, Carlos Alberto
renati.levelhttps://purl.org/pe-repo/renati/level#tituloProfesional
renati.typehttps://purl.org/pe-repo/renati/type#trabajoDeSuficienciaProfesional
thesis.degree.disciplineIngeniería Agrícola
thesis.degree.grantorUniversidad Nacional Agraria La Molina. Facultad de Ingeniería Agrícola
thesis.degree.nameIngeniero Agrícola

Files

Original bundle

Now showing 1 - 3 of 3
Loading...
Thumbnail Image
Name:
vigo-gonzales-natali-flor.pdf
Size:
3.28 MB
Format:
Adobe Portable Document Format
Description:
Texto completo
Name:
Turnitin report.pdf
Size:
3.74 MB
Format:
Adobe Portable Document Format
Description:
Informe originalidad
Name:
Anexo 9.pdf
Size:
1.52 MB
Format:
Adobe Portable Document Format
Description:
Autorización

License bundle

Now showing 1 - 1 of 1
Name:
license.txt
Size:
1.63 KB
Format:
Item-specific license agreed upon to submission
Description:

Collections